[OE-core] Yocto Project Status WW51’18

Jolley, Stephen K stephen.k.jolley at intel.com
Tue Dec 18 16:27:08 UTC 2018


Current Dev Position: YP 2.7 M1 is in QA

Next Deadline: YP 2.7 M1 Release Target is Dec. 21, 2018


SWAT Team Rotation:

·         SWAT lead is currently: Armin

·         SWAT team rotation: Armin -> Anuj on Dec. 21, 2018

·         SWAT team rotation: Anuj -> Paul on Dec. 28, 2018

·         https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

·         The next status report will be published on 2019/1/2 as we expect things to slow down over the holiday season in many locations.

·         YP 2.5.2 rc1 is out of QA and should release today or tomorrow.

·         YP 2.7 M1 is in QA.

·         The distrodata bbclass in OE-Core is being removed since the tinfoil API provides a much better way to handle this kind of issue/data.

·         We discovered potential hash collision issues with some of bitbake’s caching of objects so we are likely going to change to use sha256 everywhere including for sstate objects.

·         There are occasional issues continuing in oe-selftest which we’re struggling to get to the bottom of unfortunately.

·         There are some patches like the perl upgrade which are blocked on merging due to limited help in fixing fallout from them in layers like meta-openembedded. Khem in particular does a great job but we can’t rely on him alone.


Planned Releases for YP 2.7:

·         YP 2.7 M1 is in QA.

·         YP 2.7 M1 Release Target is Dec. 21, 2018

·         YP 2.7 M2 Cutoff is Jan. 21, 2019

·         YP 2.7 M2 Release Target is Feb. 1, 2019

·         YP 2.7 M3 Cutoff is Feb. 25, 2019

·         YP 2.7 M3 Release Target is Mar. 8, 2019

·         YP 2.7 M4 Cutoff is Apr. 1, 2019

·         YP 2.7 M4 Release Target is Apr. 26, 2019


Planned upcoming dot releases:

·         YP 2.5.2 (Sumo) is out of QA and should release shortly.

·         YP 2.6.1 (Thud) will be targeted after YP 2.7 M1 is done.

·         YP 2.5.3 (Sumo) will be targeted after YP 2.7 M2 is done.

·         YP 2.5.4 (Sumo) will be targeted after YP 2.7 M4 is done.

·         YP 2.6.2 (Thud) will be targeted after YP 2.5.4 is done.


Tracking Metrics:

·         WDD 2332 (last week 2295) (https://wiki.yoctoproject.org/charts/combo.html)

·         Poky Patch Metrics

o    Total patches found: 1629 (last week 1678)

o    Patches in the Pending State: 720 (44%) [last week 740 (44%)]


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features


The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status


[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
•    Cell:                (208) 244-4460
• Email:                             stephen.k.jolley at intel.com

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.openembedded.org/pipermail/openembedded-core/attachments/20181218/739834a5/attachment-0001.html>


More information about the Openembedded-core mailing list