[OE-core] Yocto Project Status WW28’18

Jolley, Stephen K stephen.k.jolley at intel.com
Mon Jul 9 14:59:19 UTC 2018


Current Dev Position: YP 2.6 M2.

Next Deadline: YP 2.6 M2 Build Target is July 16, 2018


SWAT Team Rotation:

·         SWAT lead is currently: Ross

·         SWAT team rotation: Ross -> Paul on July 13, 2018

·         SWAT team rotation: Paul -> Tracy on July 20, 2018

·         https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

·         2.6 M1 is out of QA and due for release this week, See: https://wiki.yoctoproject.org/wiki/WW27_-_2018-07-02_-_Full_Test_Cycle_2.6_M1_rc1.

·         QA reports for 2.3.4 and 2.2.4 should be due this week.

·         2.6 M2’s deadline is a week today.

·         Master took ~100 patches over the past week with patch review remaining roughly stable.

·         Tweaks the new autobuilder codebase mean we should have more reliable buildhistory data for master and for test branches such as -next and mut. Analysis of that data may become the problematic issue now.

·         Delays in oe-selftest execution mean we’ve started looking into solutions for increasing its parallelism once again.

·         The triage team decided to start sending out a list of the unassigned bugs once a week in the hope more people may be able to help with bugs that aren’t being actively worked on.


Planned Releases for YP 2.6:

·         YP 2.6 M1 Release Target was June 22, 2018

·         YP 2.6 M2 Build Target is July 16, 2018

·         YP 2.6 M2 Release Target is July 27, 2018

·         YP 2.6 M3 Build Target is Aug. 27, 2018

·         YP 2.6 M3 Release Target is Sept. 7, 2018

·         YP 2.6 M4 Build Target is Oct. 1, 2018

·         YP 2.6 M4 Release Target is Oct. 26, 2018


Planned upcoming dot releases:

·         YP 2.3.4 (Pyro) rc1 is built and in QA see https://wiki.yoctoproject.org/wiki/2.3_QA_Status it is at 97% complete.

·         YP 2.2.4 (Morty) rc1 is built and in QA see https://wiki.yoctoproject.org/wiki/2.2_QA_Status it is at 98% complete.

·         YP 2.5.1 (Sumo) will be targeted after YP 2.6 M2 is done.

·         YP 2.4.4 (Rocko) will be targeted after YP 2.6 M4 is done.


Tracking Metrics:

·         WDD 2646 (last week 2654) (https://wiki.yoctoproject.org/charts/combo.html)

·         Poky Patch Metrics

o    Total patches found: 1628 (last week 1640)

o    Percentage of patches in the Pending State: 761 (47%) [last week 754 (46%)]


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.6_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.6_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.6_Features


The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status


[If anyone has suggestions for other information you’d like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
•    Cell:                (208) 244-4460
• Email:                             stephen.k.jolley at intel.com

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.openembedded.org/pipermail/openembedded-core/attachments/20180709/7f54f4d5/attachment-0002.html>


More information about the Openembedded-core mailing list