Current Dev Position: YP 2.7 M2

Next Deadline: YP 2.7 M2 Cutoff is Jan. 21, 2019


SWAT Team Rotation:

*         SWAT lead is currently: Chen

*         SWAT team rotation: Chen -> Armin on Jan. 25, 2019

*         SWAT team rotation: Armin -> Anuj on Feb. 1, 2019

*         https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

*         YP 2.6.1 is out of QA and the QA results are being reviewed.  See: https://wiki.yoctoproject.org/wiki/WW02_-_2019-01-09_-_Full_Test_Cycle_2.6.1_RC1

*         We have preliminary patches for the qemuarm migration to an armv7 machine. These haven't passed testing and will need some improvements, particularly in the area of graphics support so will be deferred to M3 but it is great to see progress being made.

*         The qemu virtgl patchset is also making great progress in review/development but will also be deferred to M3.

*         We are now running the build performance tests as part of our standard autobuilder which is a further step towards streamlining our testing and release process. We are having some problems with the graphs that are generated in the emails. If anyone has experience or interest in helping with this (google charts in emails) we'd love to hear from you!

*         The perl changes which landed last week seem to have mostly been ok, there have been some race issues and we're grateful to Alex and the perl-cross upstream for their fast turnaround on those.

*         Further fixes for the gitsm fetcher landed but there are still reports of issues. We continue to try and find ways to expand our test case matrix so we can fix the issues *and* ensure we don't regress.

*         The latest round of updates from the AUH were sent out. Some have responded to this and sent in upgrades, many have not. If you are listed as a maintainer, please help us keep recipes up to date!


Planned Releases for YP 2.7:

*         YP 2.7 M2 Cutoff is Jan. 21, 2019

*         YP 2.7 M2 Release Target is Feb. 1, 2019

*         YP 2.7 M3 Cutoff is Feb. 25, 2019

*         YP 2.7 M3 Release Target is Mar. 8, 2019

*         YP 2.7 M4 Cutoff is Apr. 1, 2019

*         YP 2.7 M4 Release Target is Apr. 26, 2019


Planned upcoming dot releases:

*         YP 2.6.1 (Thud) will is out of QA.

*         YP 2.5.3 (Sumo) will be targeted after YP 2.7 M2 is done.

*         YP 2.5.4 (Sumo) will be targeted after YP 2.7 M4 is done.

*         YP 2.6.2 (Thud) will be targeted after YP 2.5.4 is done.


Tracking Metrics:

*         WDD 2421 (last week 2391) (https://wiki.yoctoproject.org/charts/combo.html)

*         Poky Patch Metrics

o    Total patches found: 1572 (last week 1565)

o    Patches in the Pending State: 677 (43%) [last week 667 (43%)]


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features


The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status


[If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
*    Cell:                (208) 244-4460
* Email:                             stephen.k.jolley at intel.com

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.openembedded.org/pipermail/openembedded-core/attachments/20190122/3e8b17d5/attachment-0001.html>


More information about the Openembedded-core mailing list