[OE-core] Yocto Project Status WW05'19

Jolley, Stephen K stephen.k.jolley at intel.com
Tue Jan 29 16:18:01 UTC 2019


Current Dev Position: YP 2.7 M3

Next Deadline: YP 2.7 M3 Cutoff is Feb. 25, 2019


SWAT Team Rotation:

*         SWAT lead is currently: Armin

*         SWAT team rotation: Armin -> Anuj on Feb. 1, 2019

*         SWAT team rotation: Anuj -> Paul on Feb. 8, 2019

*         https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


Key Status/Updates:

*         YP 2.6.1 should release this week. The transition to automated QA is raising some questions about test results but we're working through those.

*         YP 2.7 M2 was built and is in QA and is 8% done.  See: https://wiki.yoctoproject.org/wiki/2.7_QA_Status

*         There have been a further round of gitsm fixes (and new test case additions). If anyone is seeing gitsm fetcher issues please report them. There are requests to backport these changes to the stable series. This has risks but people are reporting bugs there so is something we need to consider.

*         There has been little follow up from the last round of AUH patches. Please can maintainers work on this and get these submitted!

*         There has been little feedback on the proposed virtgl changes, these will likely merge as no discussion will be taken to mean there are no objections. This will have a performance impact.

*         There have been changes to the way the arm tunes are handled which merged after much discussion. The solution that merged should be safe and uncontroversial but if these do cause problems for anyone, please report ASAP.

*         We're getting much improved results from our automated testing but these are highlighting a number of problems. There is an email about issues found in ptest. The biggest challenge here now is finding people able to step up and help improve things.


Planned Releases for YP 2.7:

*         YP 2.7 M2 is built and in QA.

*         YP 2.7 M2 Release Target is Feb. 1, 2019

*         YP 2.7 M3 Cutoff is Feb. 25, 2019

*         YP 2.7 M3 Release Target is Mar. 8, 2019

*         YP 2.7 M4 Cutoff is Apr. 1, 2019

*         YP 2.7 M4 Release Target is Apr. 26, 2019


Planned upcoming dot releases:

*         YP 2.6.1 (Thud) will release shortly.

*         YP 2.5.3 (Sumo) will be targeted after YP 2.7 M2 is done.

*         YP 2.5.4 (Sumo) will be targeted after YP 2.7 M4 is done.

*         YP 2.6.2 (Thud) will be targeted after YP 2.5.4 is done.


Tracking Metrics:

*         WDD 2393 (last week 2421) (https://wiki.yoctoproject.org/charts/combo.html)

*         Poky Patch Metrics

o    Total patches found: 1583 (last week 1572)

o    Patches in the Pending State: 677 (43%) [last week 677 (43%)]


Key Status Links for YP:

https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule

https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features


The Status reports are now stored on the wiki at: https://wiki.yoctoproject.org/wiki/Weekly_Status


[If anyone has suggestions for other information you'd like to see on this weekly status update, let us know!]

Thanks,

Stephen K. Jolley
Yocto Project Program Manager
INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124
*    Cell:                (208) 244-4460
* Email:                             stephen.k.jolley at intel.com

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.openembedded.org/pipermail/openembedded-core/attachments/20190129/aefb7fb7/attachment-0001.html>


More information about the Openembedded-core mailing list